Long Bridge (Mile 106 AHP) to the jetty end of Southwest Pass (Mile 20 Below Head of Passes ) on July 20, 2022. The maximum draft recommendation on the Ship Channel was increased to 50 feet (freshwater) from the Huey P. The areas of the Ship Channel that required dredging to provide the deeper draft channel were mechanically deepened up to Smoke Bend at Mile 175 Above Head of Passes (AHP). The USACE previously completed Phase 1 and Phase 2 of the historic project to deepen the Mississippi River Ship Channel Deepening (MRSC) to 50 Feet.

The GLENN EDWARDS is dredging under Southwest Pass Hopper Dredge Rental Contract #2-2021. Army Corps of Engineers (USACE) commenced channel maintenance dredging efforts in Southwest Pass for Fiscal Year 2023 (FY 23) on January 29, 2023, with the hopper dredge GLENN EDWARDS (Manson Construction).